You book a flat and pay a booking amount while also getting a home loan to finance the remaining payment. However after a few years you discover that the project has allegedly been abandoned by the developer. What do you do?In one such case, the District Consumer Commission ordered the real estate developer to refund the homebuyer’s booking amount, reimburse earlier EMIs and settle the loan liability.
What the case is about
A homebuyer booked a 237-square-yard residential floor in a real estate project in Sonipat in February 2017. He paid Rs 14.76 lakh towards the property and also got a home loan.According to his complaint, the possession was promised by October 2019. However, the homebuyer alleged that when he visited the construction site in December 2019, work had stopped and he learnt that the project had been abandoned.He also alleged that the finance company had disbursed Rs 67,47,091 directly to the developer without verifying the construction stage.The homebuyer said he had paid Rs 25,05,615 in EMIs and sent a legal notice in January 2020 seeking cancellation of the allotment. He relied on the tripartite agreement, arguing that the developer was responsible for repaying the loan to the finance company and returning his contribution, subject to applicable administrative charges.The real estate developer contested the complaint. It claimed that possession for fit-out purposes had been offered through a letter in August 2018, and that the homebuyer had outstanding dues. It also challenged the complaint on limitation, jurisdiction and consumer-status grounds, alleging that the property had been booked for commercial purposes. The finance company maintained that the homebuyer obligation to repay the loan continued independently of the dispute with the developer.The District Commission rejected the developer’s force majeure defence, noting that it had not produced evidence to establish that the delay resulted from circumstances beyond its control.It observed: “admittedly, there is inordinate delay in handing over the possession of the flat in question which amounts to deficiency in service.”The commission also found that the developer had not established that the homebuyer was dealing in real estate for commercial purposes. It held both respondents guilty of deficiency in service.The District Commission directed the real estate to refund Rs 14.76 lakh with interest at 9% per annum from the respective dates of deposit. If the refund was not made within four weeks of receipt of the order, the interest rate would rise to 12% per annum until realisation. It also awarded Rs 1 lakh for mental agony and harassment and Rs 25,000 towards litigation costs.Separately, the developer was directed to pay the loan amount to the finance company, reimburse the EMIs paid from May 2017 to September 2020 with interest at 9% from the date of each payment, and settle the future EMI and loan liability with the lender.
Why District Consumer Commission ruled in favour of homebuyer and State Consumer Disputes Redressal Commission dismissed later plea
However, the homebuyer appealed because he wanted reimbursement extended to the installments paid during the complaint proceedings. He sought reimbursement of EMIs paid up to May 2024, which he quantified at Rs 60,56,700. He also asked for litigation costs to be increased from Rs 25,000 to Rs 5 lakh.The State Commission noted that the finance company had not appealed against the District Commission’s order, which had therefore attained finality in relation to that respondent.It also rejected the lender’s limitation objection because the homebuyer’s application seeking condonation of delay in filing the appeal had already been allowed. Since the homebuyer’s principal grievance concerned the developer, the commission said it would not discuss the finance company’s other submissions in the appeal.The central question was whether the District Commission’s order needed modification. The State Commission examined the existing directions on reimbursement and the future loan liability.It explained: “A perusal of the above referred clause (ii) makes it clear that District Commission has not only directed OP1 to pay the EMI amount to OP 2 from May 2017 to Sept 2020, but also directed OP1 to settle the future EMI/loan amount with OP2.”The commission considered this direction sufficient to address the homebuyer’s grievance.It stated: “Since Ld. District Commission has already directed respondent1 to settle the future EMI/Loan amount with respondent no 2, we are of the considered view that the grievance of appellant has already been taken care of by Ld. District Commission.”It therefore rejected the argument that the District Commission had failed to provide for the loan liability during the complaint proceedings. It also found no grounds to increase litigation costs to Rs 5 lakh.Concluding that the original order required no modification, the State Commission observed: “Thus, in view of above discussion we find no infirmity and illegality in the impugned order passed by the Ld. District Forum which needs modification by this Commission.”The appeal was dismissed, with both sides directed to bear their own costs. The original relief remained in place, but the homebuyer did not obtain the additional modification he sought.